Back to top

Archaeological Assessment of a Coffee County Safety Improvement Project

Author(s)
Report Number
10649
Year of Publication
2005
Abstract

This proposed project consists of the installation of striping, raised pavement markings and warning signs at the following locations. All work will take place within the existing right-of-way with no new right-of-way required.

1. CR 1 - beginning at US 441 and ending at CR 553 - project length is 4.8 miles

2. CR 100 - beginning at SR 32 and ending at CR 607 - project length is 2.1 miles

3. CR 327- beginning at US 441 and ending at CR 169 - project length is 2.9 miles

4. CR 557 - beginning at Atkinson County Line and ending at SR 135 – project length is 1.6 miles

5. CR 705 - beginning at Atkinson County Line and ending at SR 158 – project length is 3.8 miles

6. CR 68 - beginning at SR 158 and ending at SR 149/CR 706- project length is 5.1 miles

7. CR 241 - beginning at CR 553 and ending at SR 64- project length is 6.1 miles