Addendum: Archeological Survey of the Proposed Bridge Replacement at SR 135 over Dark Bay Creek, Atkinson County, Georgia

Author(s)
Report Number
2730
Year of Publication
2001
Abstract

Original survey on each side of existing SR 135 was considered insufficient due to project length expansion. The current project plan shows the project end at Station 129+80.00, not Station 123+83.83 as originally planned (a difference of 483.83 ft). The current plan shows the project beginning at Station 96+00.00, not Station 100+90.00 as originally planned (a difference of 490 ft). This is an overall expansion of 296.8 m (973.83 ft).