Back to top

Archaeological Reassessment of Project BR-0001-00361, Miller County

Author(s)
Report Number
3046
Year of Publication
2005
County
Abstract

This project was originally surveyed with concurrence received in May 2003. The proposed original project consisted of replacing the existing bridge over Dry Creek on SR 91. There is approximately 100' of existing right-of-way with approximately 30' of additional right-of-way required. The original project remains unchanged except for the following: the project has been lengthened by 200' and 20' of additional right-of-way has been added. The total length of this project is 0.32 mile.