Back to top

Archaeological Assessment of Project MR-2219(1), Ben Hill County

Author(s)
Report Number
4755
Year of Publication
1988
Abstract

The proposed project would widen C.R. 206/Industrial Drive in Fitzgerald. The project would begin at S.R. 125 southwest of Fitzgerald then would extend easterly along existing C.R. 206 to S.R. 11/U.S. 129/319 where the project would turn north-northeasterly and continue northerly along C.R. 206 to S.R. 107/U.S. 319 where the proposed project would terminate. Existing right-of-way varies from a maximum of 100 feet to a minimum of 60 feet. An additional 20 feet of right-of-way would be required between C.R. 104 and C.R. 113 where existing right-of-way is 60 feet. An archaeological survey consistent with the proposed right-of-way was conducted for the entire length of the proposed project corridor. No significant archaeological resources were located within the proposed project corridor as described in paragraph two above.