Back to top

Archaeological Survey of Project NH-IM-475-1 (2-+7), Bibb County.

Author(s)
Report Number
8588
Year of Publication
2015
Abstract

The proposed project would widen Zebulon Road and the Zebulon Road bridge over I-475 in Bibb County. The project would begin 450 feet east of the I-475 northbound exit and entrance ramps and end at Lake Wildwood Drive for a total distance of 0.5 mile. The existing right-of-way is 130 feet. The required right-of-way would be 150 feet. Lamar Road on the east side of I-475 would also be relocated to tie into an existing drive.