A Cultural Resources Survey of the Proposed Water Storage Reservoir, Rabun County, Georgia

Report Number
944
Year of Publication
1987
County
Abstract

A cultural resources survey of a proposed reservoir in Rabun County was conducted in March 1587, by Elizabeth J. Misner, for the Clayton City Council. The project area includes 7.96 acres which will be impacted by the construction of a dam and associated reservoir. Impact from a new water main is judged to be minimal since it will follow an existing road. In addition to examining open ground and road cuts, the survey area was tested by placing 17 shovel tests at intervals on level areas. Two artifact occurences were noted and no archaeological sites were discovered. The unproductive shovel tests indicate that no cultural resources will, be impacted try the construction of this reservoir and the archaeologist recommends that this project be given clearance to proceed.