Back to top

SR 410 from CR 5172/Montreal Road to SR 10

Author(s)
Report Number
8845
Year of Publication
1998
County
Abstract

The proposed work consists of milling, resurfacing, leveling, patching, striping, and raised pavement markers. There are eight (8) curb cut (wheelchair) ramps to be constructed. This project will not have earth shoulder filling (adding a wedge of dirt (1 ½ inches to 0 inches) up to 4 feet wide to prevent an edge of pavement drop off then permanently stabilized same day).All paved side roads within the project limits will be resurfaced from edge of pavement to edge of pavement to back of existing radius. All unpaved roads, streets and driveways shall be paved to a distance of 15 feet from existing edge of pavement and at the existing width of road or driveway pad. No additional ROW or easement is required. Traffic disruptions associated with this project will be low intensity and of short duration and will involve no off site detours.