Archaeological Assessment of Project BRF-090-2(8), Johnson County

Author(s)
Report Number
12683
Year of Publication
1986
Abstract

Big Cedar creek-40’ x 250’ concrete bridge. A temporary detour with easement in required in the downstream side. Little Cedar creek- double 10’ x 8’ concrete bridge culvert. A temporary detour easement is required on the down stream side.