Archaeological Survey of the Proposed Cedar Creek Transmission Line, Baldwin County, Georgia

Report Number
52
Year of Publication
1977
Abstract

During the week of January 17, 1977 a survey of the Fitzgerald wastewater treatment facility was completed in order to assess the impact of the proposed construction upon cultural resources, as required by federal mandates implemented by 36 C.F.R. 800, "Procedures for the Protection of Historic and Cultural Properties." The survey, which required 2½ days' field work by one archaeologist, covered approximately 20 acres plus 3.0 miles of pipeline corridor.