Back to top

Archeological Reassessment of Project BRST-563(9), Thomas County

Author(s)
Report Number
3019
Year of Publication
2005
Abstract

The original project was surveyed and concurrence received in July 2003. This project consists of replacing the existing bridge on SR 33 over Reedy Creek south of Pavo, Georgia. The original project remains the same except for the following: the bridge has been lengthened from 80' x 38' to 260' x 38', the amount of required right-of-way has been raised from 60' to 75', the amount of temporary easement has been raised from 20' to 45', the project has been lengthened from 1600' to 2000'.