Back to top

Archaeological Assessment of Project BRF-133-1(5), Lowndes County

Author(s)
Report Number
11503
Year of Publication
1989
Abstract

Proposed structure is a triple 8’ x 6’ x 80’ concrete bridge culvert on existing alignment. The culvert is proposed to be stage constructed beginning on the south (right) side of the existing bridge and let completed section of culvert serve as run around detour while existing bridge is removed and culvert is completed. 700’ x 50’ temporary easement would be required. Approximately 85’ x 20’ permanent right of way would be required on the right side of the culvert wing walls.