Back to top

Archaeological Assessment of Project TSAP-1(102), Troup County

Author(s)
Report Number
13410
Year of Publication
1979
Abstract

Purpose is to extend the existing 9’ x 9’ bridge culvert 30 ft. to the west side and 73 ft. to the east side of the roadway. Place approximately 5400 cu. Yds. Of fill material below the 100-year highwater elevation covering approximately 1 acre. Fill material will be obtained from high land sources. Erosion control measures will be pipe slope drain, baled straw and silt control gates.