Back to top

Phase I Archaeological Survey of the Proposed Big Creek Greenway Extension, Fulton County, Georgia

Author(s)
Report Number
3789
Year of Publication
2006
Abstract

This project examined a proposed 0.75-mile greenway trail extension to the existing Big Creek Greenway. The extension will extend the Big Creek Greenway from the northern end of the existing Greenway at Webb Bridge Road to Marconi Drive. The project includes a greenway trail, pedestrian culvert crossing under Webb Bridge Road, a pedestrian bridge over Big Creek, and various site improvements. The APE is defined as the length of the project corridor and a width of 50 feet. The total APE is .75 mile long and the proposed Greenway trail is 12 feet wide. For this project, however, a 50-foot wide APE was examined along the entire project corridor during Phase I survey.