Archaeological Reassessment of Project STP-073-2(7), Appling County

Report Number
4612
Year of Publication
2001
Abstract

Project STP-073-2(7) would consist of widening and reconstructing SR 15. The proposed project would begin at CR 531/Red Oak Road and would terminate at CR 417/Hokie Floyd Road. The total length of the project is 2.86 miles. The existing right-of-way is 100 feet. The required right of way is 50 feet An archaeological survey consistent with the proposed project description was conducted along the entire length of the project corridor.