Back to top

Phase I Archaeological Survey, 1-75 Managed Lanes Concept, Forest Parkway lnterchange/NB CD System

Author(s)
Report Number
8920
Year of Publication
2015
Abstract

The project would involve construction of a CD system on the northbound side of 1-75 between Forest Parkway to the south and 1-285 to eliminate the weave between Forest Parkway traffic entering I-75 and 1-75 traffic exiting to 1-285, This would entail adding a lane to existing 1-75 between the existing northbound on and off ramps and shifting existing Frontage Road to the east. Related work will include reshaping existing slopes. The total project length is 1.4 miles.