Archaeological Assessment of GDOT Project CSSTP-0008-00(480), CR Auxiliary Exit Lane, I-95 Northbound from Jimmy Deloach Parkway to SR 21 Augusta Road in Chatham County; Pl 0008480; HP# 100913-001

Author(s)
Report Number
8244
Year of Publication
2009
County
Abstract

The proposed project consists of the construction of a continuous exit lane on 1-95 northbound from Jimmy Deloach Parkway to SR 21/Augusta Road. The exit lane would include a 12-foot lane and a 14-foot shoulder, 12 feet of which would be full depth paved leaving 2 feet to be grassed. At the I-95 northbound off ramp onto SR 21, a second 12- foot exit lane would be built and would tie-in to the existing outbound ramp, creating a total of two exit lanes. The length of the proposed project would be approximately 1.78 miles.