Back to top

Addendum to the Phase I Archaeological Survey of the SR 400 at I-285 Interchange Reconstruction, Fulton and DeKalb Counties, Georgia.

Author(s)
Report Number
9946
Year of Publication
2017
County
Abstract

The original survey for this project was conducted by GDOT personnel and reported in a GDOT Archaeological Assessment In-House Survey Report (Williams 2014). No field survey was conducted as previous archaeological surveys had covered the APE and ESC for this project. Minor alignment changes necessitated a reevaluation of the project which also determined that proposed project was covered by previous archaeological surveys (Blackwelder 2016). The entire survey area was inspected and photographed during a pedestrian survey. The shovel tests were excavated at 30-meter intervals with tests measuring 30 centimeters in diameter (Figure 3). Shovel tests were excavated to a maximum depth of 80 centimeters, or at least 10 centimeters into subsoil. All soil was screened through X inch hardware cloth.