Back to top

Archaeological Clearance of District Bridge Projects, BRSLB-2795(1)

Author(s)
Report Number
10850
Year of Publication
1979
County
Abstract

Abstract 10850

In compliance with Section 106 of the National Historic Preservation Act of 1966, the following Georgia DOT projects were surveyed for cultural resources:

COUNTY                                                                              PROJECT NUMBERS

Carroll                                                                                    BRZLB-045(1)

BRZLB-045(2 )

BRZLB-045(3)

BRZLB-045(4)

Crawford                                                                               BRZLB-079(1 )

BRZLB-079(2)

Fayette                                                                                  BRZLB-113(1)

Harris                                                                                     BRZLB-145(4)

                                                                                                BRSLB-2795(1)

Heard                                                                                     BRF-017-1(6)

BRZLB-0149(1)

BRZLB-0149(2)

Henry                                                                                     BRZ-151(002)

Houston                                                                                BRF-034-3(16)

BRF-115-1(1)

BRSLB-0668(2)

Lamar                                                                                    BRZLB-171(2)

Meriwether                                                                            BRZLB-199(3)

BRZLB-199(4)

Pike                                                                                        BRZLB-231(3)

Sumter                                                                   BRZLB-261(3)

Talbot                                                                                    BRZLB-263(2)

Troup                                                                                     BRF-010-1(19)

BRMLB-2931 (1)

Upson                                                                                    BRF-004-1 sp(31)

As many of these projects will be in-place replacements of county bridges requiring no new right-of-way, these were cleared of archaeological involvement since the right-of-way had been severely disturbed by past construction activities. Those projects requiring changes in road alignment or additional right-of-way were subjected to archaeological survey methods, including pedestrian (walk-through) survey and sub-surface testing, when necessary. No archaeological sites were encountered. Therefore, there should not be adverse impacts on the State's cultural resources connected with the above projects.