Tenth and Final Reevaluation of the Northwest Corridor Project, Cobb County, Georgia

Author(s)
Report Number
10886
Year of Publication
2018
Abstract

Project Changes for Reevaluation 10 (February 2018): P.I. No.: 0008256. The proposed project has changed to reflect the refined design location of one proposed sound barrier along the 1-75 corridor. The proposed sound barrier location, identified as 1-75 Walls 14-15, was revised due to conflicts between the sound barrier foundations and a soil nail wall for retaining Wall 49. The primary change is to shift an approximately 383-foot section of the 1-75 Walls 14-15 barrier away from the managed lanes by approximately five to 11 feet. Approximately .07 acre of new right-of-way would be required.