Back to top

Tenth and Final Reevaluation of the Northwest Corridor Project, Cobb County, Georgia

Author(s)
Report Number
10886
Year of Publication
2018
County
Abstract

Project Changes for Reevaluation 10 (February 2018): P.I. No.: 0008256. The proposed project has changed to reflect the refined design location of one proposed sound barrier along the 1-75 corridor. The proposed sound barrier location, identified as 1-75 Walls 14-15, was revised due to conflicts between the sound barrier foundations and a soil nail wall for retaining Wall 49. The primary change is to shift an approximately 383-foot section of the 1-75 Walls 14-15 barrier away from the managed lanes by approximately five to 11 feet. Approximately .07 acre of new right-of-way would be required.