Back to top

Phase I Archaeological Survey of the Proposed Replacement of the Bridge (Structure ID#121-5198-0) on CS 7001/Potomac Drive over Camp Creek, Fulton County, Georgia.

Author(s)
Report Number
13169
Year of Publication
2018
Abstract

The proposed project would consist replacing the bridge carrying CS 7001/Potomac Drive over Camp Creek in Fulton County, Georgia (Figure 1). The existing facility along Potomac Drive consists of two 14-foot with urban shoulders south of bridge and rural shoulders north of the bridge. The proposed project would replace the existing structure with a new bridge consisting of two 12-foot lanes with 5.5 foot sidewalks on either side. Existing right of way (ROW) measures 40 feet on Potomac Drive. The project also includes 30 feet of Required ROW on the east side of the bridge and 10 feet of easements on the west side of the structure.