Archaeological Reassessment of Project NH-IM-185-1(317), Muscogee County

Author(s)
Report Number
2992
Year of Publication
2005
County
Abstract

This project was originally surveyed and concurrence received in September of 1997. The project proposes to add an additional inside lane to 1-185. The existing right-of-way on 1-185 is approximately 200', with approximately 50' of additional right-of-way required for project implementation. The areas of the project located within Fort Benning boundaries, have been previously surveyed and cleared for archaeological resources (see attachment email). The original project remains the same, except for the following: the amount of required right-of-way has been changed from approximately 50' to approximately 100' 170'. The total length of this project is 0.94 mile.