Reevaluation of the Northwest Corridor Project, Phase II, Cobb County, Georgia

Author(s)
Report Number
7616
Year of Publication
2010
Abstract

This project is a Design, Build, Finance (DBF) project and has been procured as a Public-Private Partnership (P3). As part of the design-build process, the P3 Developer has identified five areas for Phase 2 construction. On the Developer's construction phasing plan (see attached), these areas are identified as: • Phase II Roadway Package A • Phase II Roadway Package B 1 • Phase II Roadway Package B2 • Phase II Roadway Package C • Phase II Roadway Package D Changes in design in these five areas are summarized below.