Transcontinental Gas Pipeline Company, LLC (Transco) is seeking a Certificate of Public Convenience
from the Federal Energy Regulatory Commission (FERC) pursuant to Section 7 (c) of the Natural Gas Act
for the construction and operation of a 111.7-mile natural gas pipeline (the Project) in northwestern Georgia.
An initial report of archaeological survey for the Project was submitted to the Georgia Historic Preservation
Division (HPD Project # HP-140603-005) and filed with Transco’s FERC application in March 2015 (FERC
Docket No. CP15-117-000).
The Project consists of a new lateral pipeline, the Dalton Lateral, beginning at Transco’s Compressor
Station 115 in Coweta County, and ending near Dalton, Georgia. The line would extend through eight
counties in northwest Georgia to Murray County. The Project will consist of 111.7 miles of new natural gas
pipeline in three continuous segments (Dalton Lateral Segments 1, 2, and 3) and a new 2.0-mile natural
gas lateral pipeline spur (the AGL Spur). A new compressor station and three new meter stations also will
be constructed, and modifications and supplemental odorization equipment will be installed at existing
facilities as part of the Project.
Between June 2014 and October 2015, Cardno conducted Phase I survey of the Project within Georgia.
Cardno identified 127 archaeological sites and 62 isolated finds (IFs) within the project’s area of potential
effect. This report presents the results of Phase II archaeological site testing at a site located in northcentral
Gordon County, 9GO394. Cardno conducted the Phase II investigation between April 26 and May
4, 2016. The purpose of the current archaeological investigation was to determine if site 9GO394 meets
the minimum requirements for inclusion in the NRHP. Archaeological deposits would be eligible for inclusion
in the NRHP under Criterion D if they have the potential to yield significant data relating to the prehistory or
history of the region.
Phase I testing at 9GO394 identified a subsurface artifact scatter yielding almost exclusively historic
artifacts and which included a domicile, a barn, and a well pad and dated to the very late nineteenth through
twentieth centuries. The site retained a relatively high degree of integrity and archaeological deposits
appeared intact and seemed to represent a discrete domestic refuse disposal area, suggesting that the
overall level of subsurface integrity is very high. Given this, Cardno recommended that 9GO394 is eligible
individually for the NRHP under Criterion D and also as a contributing resource to the Harlan McDaniel
house. Avoidance of the house, barn, and archaeological site extents described in the Phase I testing report
was recommended. Cardno also recommended additional archival research mapping and testing in order
to complete an evaluation of the historic sites’ eligibility for the NRHP and to assess negative effects.
During Phase II testing at 9GO394, additional work included the excavation of two test units along with
eight shovel tests and additional metal detection survey. Following the Phase II investigation, the site
boundaries have been expanded to include three spatially distinct site areas. From east to west the site
areas include (1) the dilapidated structures and midden within the Phase I boundary of 9GO394, (2) the
diffuse scatter of agricultural debris in the lawn east of the Harlan-McDaniel house, and (3) the Harlan-
McDaniel house and associated structures. Although the historic structures at the Harlan-McDaniel property
have been well documented during Cardno’s historic resources survey (Jones 2016), their assessment as
components of an archaeological site must be considered unknown, because they are outside the limits of
the survey corridor. Following HPD guidance, they are therefore included within an unknown archaeological
site boundary, depicted in dotted green on Figure 21 (Chapter 6, site excavations).
Of the three site areas described in this Phase II report, Area 1 (the farmstead and midden on the east of
the site) and Area 3 (the Harlan-McDaniel structures in the west of the site) are both considered to retain
Phase II Archaeological Testing of Site 9GO394
Dalton Expansion Project, Gordon County, Georgia
July 2016 Cardno Executive Summary
GO394PhaseII integrity and the potential for additional data recovery. Therefore, the site as a whole is
recommended eligible for the NRHP. Aside from the aforementioned artifact scatter possily related to a
structure, the portion of Area 2 impacted by construction was found to lack integrity and data potential.
The area around the artifact scatter in Area 2 has been designated as a culturally sensitive area and
barier fencing will be erected to protect from constructioin-related damage. Please see Section 6.1.4 of
this report for a more thorough discussion of these findings. Because both the structures at Area 3 and
the archaeological remains and structures at Area 1 are outside of Project workspaces, neither will be
impacted by a direct effect of construction. They will be protected by indirect effects of construction
activity by fencing around workspaces (Figure 1). An archaeological monitor will be present during the
time of construction. Therefore the Project will have no adverse effect on the properties as currently
designed.