Back to top

Culvert Repair: 1-75 southbound (SB) ramp to 1-285 eastbound (EB) over Mud Creek

Report Number
8890
Year of Publication
1985
Abstract

The proposed project would consist of the repair of cracks, correction of erosion issues, joint sealing, replacement of separated wing walls, debris removal, and concrete repair as well as scour work and the addition of a toe wall at the inlet and outlet sides of a culvert at the 1-75 SB ramp to 1-285 EB over Mud Creek. All work will take place within existing right-of-way (ROW). Area of Potential Effect: Because of the nature and scope of the undertaking, the APE is limited to the existing ROW of the proposed project, within which all construction and ground disturbing activity would be confined. The 100-ft. expanded survey corridor (ESC) was not evaluated for this project.