Archaeological Assessment of BHF-052-2(20), Jackson County

Report Number
8369
Year of Publication
2012
County
Abstract

The proposed project consists of the widening and replacement of the bridge on SR 15 Alt. over Curry Creek in the city of Jefferson. The project would replace the existing bridge with a 5 barrel culvert. The project would begin approximately 124 m (407 ft) west of Curry Creek and ends approximately 224 m (735 ft) east of Curry Creek. The existing right-of-way is approximately 15 m (50 ft) . Required right-of-way varies from approximately 32 m (105 ft) to 76 m (250 ft) . An archaeological survey consistent with the project description was conducted along the entire project corridor.