8274
|
DuBois, Autumn, Bazzill, Dina M.
|
Archaeological Assessment TCNS ID #123867 Proposed 200-Foot (Overall Height) Monopole Telecommunications Structure Within an Approximate 70-Foot by 70-Foot (21-Meter by 21-Meter) Lease Area American Towers LLC- 281728 (Glenwood 4 RELO GA) Attachment E Pag
|
Environmental Corporation of America (ECA) has completed an Archaeological Assessment for the federal undertaking at the project area.
|
Clayton
|
2011
|
9053
|
Vargas, Jessica, DuBois, Autumn
|
TCNS ID 133463 Proposed 150-Foot Monopole Communications Structure (163-Foot Overall Height Including Appurtenances)
|
Environmental Corporation of America’s (ECA) client, Georgia Power Company, is proposing to construct a communications facility as described in the following FCC Form 620, New Tower (NT) Submission Packet.
|
Walton
|
2006
|
9074
|
Nuss, Andrew, DuBois, Autumn
|
Archaeological Assessment TCNS ID #133596 Proposed 150-foot Monopole Communications Structure (163-Foot Overall Height with Appurtenances) Within An 8-Foot by 8-foot
|
Environmental Corporation of America (ECA) has completed an Archaeological Assessment for the federal undertaking at the subject site.
|
Fulton
|
2010
|
9513
|
DuBois, Autumn, Vargas, Jessica
|
TCNS ID 136030 Tifton Operating Headquarters Bruce Lane Tifton, Tift County, Georgia ECA Project No. S0416
|
Environmental Corporation of America’s (ECA) client, Georgia Power Company, is proposing to construct a communications facility as described in the following FCC Form 620, New Tower (NT) Submission Packet.
|
Tift
|
2016
|
9516
|
DuBois, Autumn
|
Section 106 Review TCNS ID 134398 Proposed 158-Foot Monopole Telecommunications Structure (162-Foot Overall Height with Appurtenances) Beacon Towers, LLC – Douglas Bypass 263 Monica Leigh Lane, Douglas, Coffee County, Georgia ECA Project No. R1630
|
Environmental Corporation of America’s (ECA) client, Beacon Towers, LLC is proposing to lease a 100-foot by 100-foot (~30-meter by 30-meter) area for the construction of a telecommunications facility as described in the following FCC Form 620, New Tower (NT) Submission Packet.
|
Coffee
|
2016
|
9519
|
DuBois, Autumn, Vargas, Jessica
|
Section 106 Review: TCNS ID 134408 Proposed 400-Foot Tall Guyed Telecommunications Structure (420-Foot Overall Height Including Appurtenances) G8606 (Berlin) Off of GA-133 Berlin, Colquitt County, Georgia ECA Project No. R1622
|
Environmental Corporation of America’s (ECA) client, Southern Communications Services, d/b/a SouthernLINC Wireless c/o Value Concepts, Inc., is proposing to construct a telecommunications facility as described in the following FCC Form 620, New Tower (NT) Submission Packet.
|
Colquitt
|
2016
|
9534
|
Vargas, Jessica, DuBois, Autumn
|
Section 106 Review: TCNS ID 133466 Proposed 150-Foot Monopole Communications Structure (163-Foot Overall Height Including Appurtenances) East Lumpkin Substation Broad Street Lumpkin, Stewart County, Georgia ECA Project No. R1546
|
Environmental Corporation of America’s (ECA) client, Georgia Power Company, is proposing to construct a communications facility as described in the following FCC Form 620, New Tower (NT) Submission Packet.
|
Stewart
|
2015
|
9720
|
DuBois, Autumn
|
Section 106 Review TCNS ID 154689 Proposed 120-Foot Tall Pole Communications Structure (123-Foot Overall Height Including Appurtenances)
|
Environmental Corporation of America’s (ECA) client, Mobilitie, LLC, is proposing to construct a pole as described in the following FCC Form 620, New Tower (NT) Submission Packet.
|
Emanuel
|
2017
|
9724
|
DuBois, Autumn
|
Section 106 Review TCNS ID 154704 Proposed 120-Foot Tall Pole Structure (123-Foot Overall Height Including Appurtenances)
|
Environmental Corporation of America’s (ECA) client, Mobilitie, LLC, is proposing to construct a pole as described in the following FCC Form 620, New Tower (NT) Submission Packet.
|
Warren
|
2017
|
9728
|
DuBois, Autumn
|
Section 106 Review TCNS ID 148964 Proposed 123-Foot Tall Overall Height Pole Structure
|
Environmental Corporation of America’s (ECA) client, Mobilitie, LLC, is proposing to construct a pole as described in the following FCC Form 620, New Tower (NT) Submission Packet.
|
Clayton
|
2017
|