Back to top

Hart, Barry D.

Report Number Author(s) Title Abstract Summary County Year
593 Hart, Barry D. An Intensive Archaeological Survey of Dot Project Brf 04628 Within Oconee National Forest, Greene County

Project #BRF-046-2(80) consists of replacing, on new alignment, th U.S. 278/S.R. 12 bridge over the Oconee River (Figure 1 and 2).

Greene 1983
4671 Hart, Barry D. Archaeological Assessment of Project SR 0777(6), Baldwin County

This project will correct hazardous horizontal alignment on S.R. 212 from M.P. 7.06 to M.P. 7.55 north of Milledgeville. The new centerline will shift slightly south of the existing centerline. A 120 foot wide corridor was surveyed for the length of the project.

Baldwin 1985
4733 Hart, Barry D. Archaeological Assessment of Project BRS-2725(2), Berrien County

The bridge on S.R. 37 over Beaverdam Creek will be replaced on existing location. Construction will be maintained to the existing 100 feet of right-of-way. A corridor 100 feet wide and 1700 feet long was surveyed for the project.

Berrien 1984
4741 Hart, Barry D. Archaeological Assessment of Project BRF-079-1(14), Cook-Berrien Counties

The bridges on S.R. 76 over Young's Mill Creek and New River will be replaced on existing alignment. Young's Mill Creek will be replaced on the 100' of existing right-of-way. This corridor was surveyed for a length of 2300 feet.

Berrien 1984
4848 Hart, Barry D. Archaeological Assessment of Project FR-068-1(19), Evans/Bulloch County

The project involves the widening of U.S. 301 from the existing 5 lane section in Claxton north to 1-16. A 200 foot wide corridor was surveyed for the length of the project.

Bulloch 1985
4938 Hart, Barry D. Archaeological Assessment of Project EDFR-HES-159-1(12), Coweta County

S.R. 16 will be widened within existing right of way for approximately 50() feet each direction (north and south) at the intersection of S.R. 34. S.R. 34 will also be widened within existing R/41 from the S.R. 34/S.R. 16 .intersection to Belk Road.

Coweta 1985
4969 Hart, Barry D. Archaeological Assessment of Project BRS-0535(4), Crisp County

No existing or eligible. National Register archaeological resources were located within the project's area of potential environmental effect.

Crisp 1984
5022 Hart, Barry D. Archaeological Assessment of Project BRF-083-1(27), Calhoun County

No significant archaeological resources were located within the proposed project corridor as described in paragraph two above.

Glynn 1995
5123 Hart, Barry D. Archaeological Assessment of Project FR-064-1(25), Chatham County

The proposed project will provide an additional passing lane between M.P. 28.5 and 30.9. The project will be completed within the existing 150 feet of rightof-way. A 150 foot corridor was surveyed for the length of the 1.4 mile project.

Chatham 1996
5301 Hart, Barry D. Archaeological Assessment of Project IR-75-3(148), Whitfield County

No significant archaeological resources were located within the proposed project corridor as described in paragraph two above.

Whitfield 2002
Displaying 1 - 10 of 142