Back to top

Hart, Barry D.

Report Number Author(s) Title Abstract Summary County Year
5448 Hart, Barry D. Archaeological Assessment of Project FR-104-1(28), Dekalb County

No significant archaeological resources were located within the proposed project corridor as described in paragraph two above.

DeKalb County, GA 1989
5495 Hart, Barry D. Archaeological Assessment of Project BRZLB-291(6), Union County

No significant archaeological resources were located within the proposed project corridor as described in paragraph two above.

Walker County, GA 1980
5506 Hart, Barry D. Archaeological Assessment of Project BRZLB-057(13), Cherokee County

No significant archaeological resources were located within the proposed project corridor as described in paragraph two above.

Decatur County, GA 1996
5532 Hart, Barry D. Archaeological Assessment of Project FR-187-1(10), Cherokee County

No significant archaeological resources were located within the proposed project corridor as described in paragraph two above.

DeKalb County, GA 1995
6006 Hart, Barry D. Archaeological Assessment of Project BFR-036-1(8), Coffee County

An archaeological survey (Level I ) was conducted in accordance with "GDOT Archaeological Survey Guidelines" developed by the GDOT Staff Archaeologists in consultation with DNR Historic Preservation Section Staff and concurred in by the Federal Highway Administration and State Historic Preservat

Henry County, GA 2010
6008 Hart, Barry D. Archaeological Assessment of Project FR-023-2(5), Coffee County

The project involves the replacement of the bridge over Seventeen Mile River on S.R. 31/U.S. 441. The bridge will be replaced within the existing 100200 feet of right-of-way.

Fulton County, GA 2010
6322 Hart, Barry D. Archaeological Assessment of Project M-178-1(18), Cobb County

The project will begin on Lower River Road and will move on new location northwest to intersect Six Flags Road at the Six Flags Road/I-20 intersection. A 350 foot corridor was cleared for the length of the project along the proposed centerline,

Wilkes County, GA 1976
6329 Hart, Barry D. Archaeological Assessment of Project TSAP 120 (42) Cobb county

This is a road widening and improvement project on S.R. 120, from Sewell Mill Road to Johnson Ferry Road. A 110 foot wide corridor was surveyed.

Wilcox County, GA 2001
6465 Hart, Barry D. Archaeological Assessment of Project BRZLB-107(8), Emanuel County

The project involves the replacement of the bridge on C.R. 252 over Jack's Creek. An 80 foot corridor is required for the project length, beginning 1250 feet southwest of the existing bridge and terminating 600' northeast of that facility.

Clayton County, GA 1983
6499 Hart, Barry D. Archaeological Assessment of Project BRF-068-1(16)

The purpose of the survey was to locate, identify and evaluate the significance of any archaeological resources within the project corridor.

Cobb County, GA 1985
Displaying 11 - 20 of 142