4759
|
Duff, Eric Anthony, McIntosh, Paul
|
Archaeological Assessment of Project PR-358-2(019), Berrien County
|
Project PR-358-2(019) involves the widening, leveling and resurfacing of CR 358 (Tetterville Road) in Berrien County. The project would begin at the Lanier County line and would extend northward to end at the intersection of SR 168. The existing right-of-way is approximately 80 ft.
|
Berrien
|
2000
|
4776
|
Duff, Eric Anthony, Lotti, Teresa Ann
|
Archaeological Reassessment of Project BRZLB-25(6), Brantley County
|
Project BRZLB-25(6) consists of the replacement of a narrow and substandard bridge on CR 191 over the South Prong of Big Creek in Brantley County, Georgia. This project has been subjected to two previous surveys by Erica Jeter, the first in 1999 and the second in 2001.
|
Brantley
|
2002
|
4777
|
Duff, Eric Anthony, McIntosh, Paul
|
Archaeological Assessment of Project PR-8530(025), Brantley County
|
The proposed project would consist of grading, drainage, base and paving of four city streets in the city of Hoboken. The streets involved are as follows: Chickasaw Road, Coweta Road, Azalea Drive and Dogwood Drive.
|
Brantley
|
2001
|
4778
|
Duff, Eric Anthony
|
Archaeological Assessment of Project BRZLB-25(5), Brantley County
|
The proposed project would replace the structurally deficient bridge on CR 11 over Mil-1- Creek in Brantley County. The proposed bridge project on CR 11 would begin approximately 106 meters (350 feet) south and end approximately 106 meters (350 feet) north of the existing bridge over Mill Creek.
|
Brantley
|
1996
|
4805
|
Duff, Eric Anthony, McIntosh, Paul
|
Archaeological Assessment of Project STP-1300(4), Crisp County
|
The proposed project would consist of a grade separation and bridge construction at the 24th Avenue intersection with the Norfolk Southern Railway in Crisp County. The bridge would be a 345-foot X 45foot structure with two 12-foot travel lanes, curb and gutter, sidewalks and retaining walls.
|
Crisp
|
2001
|
4809
|
Duff, Eric Anthony, McIntosh, Paul
|
Archaeological Reassessment of Project BHF-038-2(40), Emanuel/ Burke Counties
|
The original proposed project would replace the SR 56 bridge over the Ogeechee River, plus the two overflow bridges south of the river. All three will be widened from 25.8 feet to 40 feet.
|
Burke
|
2003
|
4822
|
Duff, Eric Anthony, Fleming, Sherry
|
Archaeological Assessment of Project STP-014-1(65), Screven/ Burke Counties
|
The proposed project would consist of plant mix resurfacing of State Route 24 beginning at MP 31.34 in Screven County and ending at MP 3.46 in Burke County. All disturbance will be confined to the area of the existing pavement.
|
Burke
|
1995
|
4829
|
Duff, Eric Anthony
|
Archaeological Assessment of Project STP-149-1(29), Bulloch County
|
The proposed project would widen SR 67 from CR 248/585 to the existing curb and gutter section on SR 67 inside the city limits of Statesboro for a total distance of approximately 2.25 kilometers (1.4 miles) .
|
Bulloch
|
1995
|
4831
|
Duff, Eric Anthony, Lotti, Teresa Ann
|
Archaeological Assessment of Project STP-0001-00(076), Bulloch County
|
STP-0001-00(076) would relocate a portion of CR 9/Akins Pond Road in Bulloch County, Georgia. The proposed project would realign the southern terminus of CR 9/Akins Pond Road to provide a 90-degree intersection with SR 26/US 80. The shift would require 80 feet of right-of-way on new location.
|
Bulloch
|
2002
|
4834
|
Duff, Eric Anthony
|
Archaeological Reassessment of Project STP-149-1(29), Bulloch County
|
Project STP-149-1(29) would widen and reconstruct SR 67 in Bulloch County.
|
Bulloch
|
2000
|