1163
|
Smith, Greg C., Ashley, Keith H.
|
An Intensive Cultural Resource Assessment of the Jimps Tap Transmission Line Corridor
|
In December 1993, Environmental Services, Inc., conducted an intensive cultural resource assessment survey of a 1.6 mile long by 75 foot wide corridor in Bulloch County, Georgia. The corridor is the proposed location for Oglethorpe Power Corporation's Jimps Tap 115 kV Transmission Line Project.
|
Bulloch
|
1993
|
1175
|
Smith, Greg C., Ashley, Keith H.
|
An Intensive Cultural Resource Assessment Survey of the Proposed Eci Tap 46kv Transmission Line Corridor and Proposed Eci 46/25kv Substation
|
A cultural resource assessment survey was conducted of the proposed ECI Tap 46 KV Transmission Line and proposed ECI 46/25 KV Substation, Emanuel County, Georgia in April 1994.
|
Emanuel
|
1994
|
1256
|
Ashley, Keith H.
|
A Cultural Resource Assessment Survey of the Proposed Harry S. Truman Parkway Extension Corridor, Chatham County, Georgia
|
A cultural resource assessment survey was conducted of the proposed Harry S. Truman Parkway extension corridor, Chatham County, Georgia in September 1993. The survey corridor was approximately 4.1 miles in length, with an average width of 200 feet.
|
Chatham
|
1994
|
1333
|
Ashley, Keith H., Chance, Marsha A.
|
An Archaeological Survey of the US 27 Widening Project LaGrange to the Roopville Bypass
|
An archaeological assessment survey was conducted by Environmental Services, Inc. (ESI) of a segment of U.S. 27 through Troup, Heard, and Carroll Counties, Georgia, between December 1993 and February 1994.
|
Carroll
|
1995
|
1422
|
Ashley, Keith H.
|
An Intensive Cultural Resource Assessment Survey of the Proposed Hopeful-Mt. Olive 46kv Transmission Line
|
A cultural resource assessment survey was conducted of the proposed Hopeful-Mt. Olive transmission line, Mitchell County, Georgia in September 1995.
|
Mitchell
|
1995
|
1518
|
Ashley, Keith H., Rolland, Vicki
|
An Intensive Cultural Resource Assessment Survey of the Proposed Ling Reach 115kv Tap Transmission Line Corridor and Proposed Long Reach 115/25 Kv Substation
|
A cultural resource assessment survey was conducted of the proposed Long Reach 115 kV Tap Transmission Line Corridor and Long Reach 115/25 kV Substation, Long County, Georgia in July 1996.
|
Long
|
1996
|
4478
|
Ashley, Keith H., Bland, Myles
|
An Intensive Cultural Resource Assessment Survey of the Baisden Bluff Parcel, McIntosh County, Georgia
|
From June 20 to 23, 2006, an intensive cultural resource assessment survey was conducted of a 9acre tract in northern McIntosh County, Georgia. The project tract is the proposed site of the Baisden Bluff development. The present project was undertaken by Bland and Associates, Inc.
|
McIntosh
|
2007
|
4800
|
Smith, Greg C., Ashley, Keith H.
|
A Cultural Resource Assessment Survey of the Proposed Genesis Point Marina Bryan County, Georgia
|
A cultural resource assessment survey was conducted of the proposed Genesis Point Marina, Bryan County, Georgia from December 1994 to January 1995. The Phase I archaeological investigation included a pedestrian survey of the 20 acre tract with systematic shovel testing at 30 meter intervals.
|
Bryan
|
1995
|
6664
|
Smith, Greg C., Ashley, Keith H.
|
A Cultural Resource Assessment Survey for the Proposed Expansion of the Lamar County Landfill,Lamar County, Georgia
|
During June 1997, an intensive cultural resource assessment survey was conducted of an approximately 145 acre tract in Lamar County, Georgia.
|
Gwinnett
|
1993
|
9270
|
Smith, Greg C., Chance, Marsha A., Ashley, Keith H.
|
A Cultural Resource Assessment Survey for the Proposed FSL Landfill, Forsyth County, Georgia
|
In April 1996, a cultural resource assessment survey was conducted of an undeveloped tract (approximately 500 acres) above the western floodplain of the Etowah River in Forsyth County, Georgia.
|
Forsyth
|
1998
|