11236 Entorf, Bob P. Archaeological Assessment of Project BRF-170-1(3), Carroll County

410’ x 25’ bridge w timber and concrete piles, timber caps, steel beams, and concrete deck, estimated 80’ row. Bridge for S.R. 100 over Little Tallapoosa River. Classified as a fishing river. Estimated 480’ x 44’ bridge and estimated row 100’.

Carroll 1988
11237 Entorf, Bob P. Archaeological Assessment of Project BHF-022-1(18), Butts County

278’ x 23.9’ bridge with concrete columns and a substrate deck, 100’ row. Bridge for S.R. 16 over Towaliga River. Widen existing bridge to 44’ width 100’ row.

Butts 1989
11238 Bowen, William R. Archaeological Assessment of Project BRZLB-13(5), Barrow County

Existing structure is a 30’ long x 15.5’ wide bridge. Earth abutments, steel stringers, wood deck (poor condition). 30’ total existing R/W. Proposed 50’ double + double 10’ X 6’ concrete bridge culvert on existing alignment. Road to be closed during construction.

Barrow 1987
11239 Bowen, William R. Archaeological Assessment of Project BRZLB-13(8), Barrow County

Existing wood and steel I-beam bridge 26’ x 14’. 60’ total existing right of way. Replace existing bridge at present location with proposed 40’ triple 8’ x 5’ concrete bridge culvert. Road to be closed during construction. Easements to be acquired by county.

Barrow 1987
11240 Bowen, William R. Archaeological Assessment of Project BRS-0910, Barrow-Jackson Counties

22’ x 245’ concrete structure with guardrail handrail. 100’ existing R/W. Replace existing bridge with a 38’ x 220’ bridge. No R/W required. Retain existing alignment. No detour required. Road to be closed during construction.

Barrow 1988
11241 Paglione, Teresa L. Archaeological Assessment of Project BRZLB-199(10), Meriwether County

23.9'X 97' bridge with timber pilings and a concrete deck. Approaches are 677' in length and have 21' paving with 5'shoulders. Existing right-of-way is 80'. Replace bridge on existing alignment with a 30'X 130' concrete bridge .

Meriwether 1988
11242 Paglione, Teresa L. Archaeological Assessment of Project BRZLB-207(14), Monroe County

43'X12.3 ' bridge with concrete substructure, steel main support, and timber derl 35' right-of- way. Begins approx. 0.25 mile west of creek and ends approx. 0 . 25 mile east of creek . Replace on existing location with triple 9'X8' bridge culvert. 100' right- of- way required.

Monroe 1993
11243 Paglione, Teresa L. Archaeological Assessment of Project BRZLB-015(8), Bartow County

Bridge over Connesena Creek using county Road 78/Old Rome Road. Existing structure is a 15.7’ wide x 60’ long concrete decked over steel stringer beam bridge with no handrails or guardrails. Existing right of way 40’. Proposed project begins approx. 300’ west of Connesena Creek and ends approx..

Bartow 1986
11244 Entorf, Robert F. Archaeological Assessment of Project BRZLB-015(9), Bartow County

Existing structure a 119’ x 15.8’ wood deck bridge. Existing right of way 30 feet. Begins 700’ northwest of bridge and ends 500’ southeast of bridge. Replace existing bridge with a double double 9’ x 9’ concrete bridge culvert approx. 50 feet southwest of existing bridge.

Bartow 1988
11245 Rotenstein, David S. Archaeological Assessment of Project BRZLB-19(6), Berrien County

48’ x 16’ at Tenmile creek and 5-36” metal pipe at tenmile creek tributary, timber bridge, no existing row. A proposed double, double 6’ x 6’ x 36’ bridge culvert at tenmile creek and a 9’ x 5’ x 36’ box culvert at the Tributary. To be replaced on existing alignment.