Back to top

Report Abstracts

Report Number Author(s) Title Abstract Summary County Year
11878 Bowen, William R. Archaeological Assessment of Project RS-0953(11) Effingham County

In compliance with Section 106 of the National Historic Preservation Act of 1966 and amendments thereto, project RS-0953(11), Effingham, has been surveyed with respect to archaeological resources, especially those on or eligible for inclusion in the National Register of Historic Places (NRHP).

Effingham 1984
11879 Paglione, Teresa L. Archaeological Assessment of BRS-1197(7), Decatur County

Bridge over Big Slough Creek is proposed to be, replace on existing alignment with a 180’ x 38’ concrete bridge. Road shall be closed during construction and traffic would be maintained on other routes. No additional right of way would be required.

Decatur 1990
11880 Entorf, Robert F. Archaeological Assessment of Project BRZLB-087(6), Decatur County

Proposed triple 10’ 6’ x 36’ concrete bridge culvert on existing alignment. Eighty feet of right of way will be required for construction. Road will be closed during construction.

Decatur 1987
11881 Richardson, Rick R. Archaeological Assessment of Project BRF-038-2(30), Emanuel County

New structures will be a triple 9’ x 8’ x 50’ bridge culvert, a double 7’ x 6’ x 50’ box culvert, a triple 9’ x 8’ x 50’ bridge culvert, a triple 9’ x 8’ x 50’ bridge culvert and a 40’ x 320’’ bridge, respectively.

Emanuel 1992
11882 Entorf, Robert F. Archaeological Assessment of Project BRZLB-115(11), Floyd County

Beginning bridge approximately 100 feet from new structure, ends approximately 72 feet from new structure. Required right of way 15 and 10 feet left and 5 and 25 feet right. Required 43 feet triple 7 x 5 concrete bridge culverts. No detours required. Road to be closed during construction.

Floyd 1987
11883 Entorf, Robert F. Archaeological Assessment of Project BRZLB-115(9), Floyd County

Begins approximately 800’ south of creek and ends approximately 800’ north of creek. New structure a concrete bridge. 200’ long x 28’ wide. Required right of way 80.’ Existing structure to be closed during construction-county to provide detour.

Floyd 1987
11884 Duff, Eric Anthony Archaeological Assessment of Project BRS-0577(15), Emanuel County

The project begins approximately 241.40, west of the stream and ends approximately 241.40m east of the stream. The new structure will be a 9.75m x 121.92, concrete bridge. No additional right of way will be required.

Emanuel 1994
11885 Erickson, Luke W. Archaeological Assessment of a Pickens County Road Improvement Project

Archeological Assessment o f a Pickens County Road Improvement Project.

Pickens 2005
11886 Entorf, Robert F. Bridge Categorical Exclusion, BRSLB-2294(1) Floyd County

This is a bridge project, BRSLB-2294(1), located in Floyd County. The bridge is on CR 129 and crosses Dykes Creek. The existing structure is a 51 feet long by 16 foot wide bridge with concrete piers and abutments as well as a two span concrete slab. The existing ROW is 60 feet.

Floyd 1989
11887 Erickson, Luke W. Archaeological Assessment of a Fannin County Resurfacing Project, CSSTP-0007-00(470)

Archaeological Assessment of a Fannin County Resurfacing Project: This proposed project consists of striping the thermoplastic centerline, edge lines, symbol markings, paint striping, stop bars, and installing new signage on Aska Road and Mobile Road, Fannin County, Georgia and Polk County, Tenne

Fannin 2005