Back to top

Report Abstracts

Report Number Author(s) Title Abstract Summary County Year
6537 Rotenstein, David S. Archaeological Assessment of Project IR-75-2(155), Henry/Clayton Counties, November 1986

This is the proposed within-median widening of Interstate 75 from a point just south of 1-675 to a point just south of 1-285. The total length of the project is 10.9 miles.

Henry County, GA 1986
6538 Entorf, Robert F. Archaeology Assessment of Project BHM-9097(6), Clayton County

Proposed project would symmetrically widen existing bridge structure on N. Main St./Old S.R. 3 at Jester's Creek. The proposed project would require 100 feet of right of way with temporary construction easements. Existing right of way is 80 feet.

Glynn County, GA 1990
6539 Paglione, Teresa L. Archaeological Assessment of Project FR-164-1(28), Project IR-75-2(170), and Project IR-75-2(174), Clayton County

Project FR-164-1(28) Spur consists of the widening and reconstruction of SR 54 beginning at the intersection of SR 138 Bypass in Jonesboro and extending 1000 feet north of the intersection with oxford Drive in Morrow, with a 1200 foot exception for project IR-75-2(174).

Glynn County, GA 1987
6540 Paglione, Teresa L. Archaeological Assessment of Projects MR-9108(5) and BHMLB-9108(3), Clayton County

Project MR-9108(5) consists of the widening and reconstruction of Battlecreek Road from Valley Hill Road east to Southlake Parkway in Morrow. Project BHMLB-9108(3) would be the replacement of the bridge over Jesters Creek.

Clayton County, GA 1973
6541 Paglione, Teresa L. Archaeological Assessment of ProjectMR-9109(1), Clayton County

Project MR-9109(1) consists of the widening of Mt. Zion Road in Morrow from Jonesboro Road/S.R. 54 to the intersection with Mt. Zion Boulevard. The existing right-of-way is 80 feet; the required right-of-way would be 90 feet.

Fulton County, GA 1973
6542 Paglione, Teresa L. Archaeological Assessment of Project MR-9107(2), Clayton County

Project MR-9107(2) consists of the widening of Flint River Road. The project begins at Webb Road and continues east toward Tara Boulevard/U.S. 19/U.S. 41. Intersection improvements at Webb Road, Kendrick Lane, and Roberts Road will be on new location.

Clayton County, GA 1973
6543 Danchetz, Frank L. Archaeological Assessment of Project MR-9113(3), Clayton County

The proposed project would widen Anvilblock Road east of Fort Gillem. The project as proposed would begin at a point approximately 3300 feet east of the 1-675 interchange then would extend easterly along existing Anvilblock Road to the intersection of Bouldercrest Road.

Clayton County, GA 1976
6544 Fernandez-Sardina, Ricardo Archaeological Reassesment of Project STP-164-1(64), Clayton/Henry Counties

The proposed project would widen and reconstruct SR 138 from 1-75 west to! Jonesboro. A minimum 160 feet right-of-way is required to widen the_ existing two-lane to a divided four-lane roadway.

Fayette County, GA 1976
6545 Paglione, Teresa L. Archaeological Assessment of Project FR-001-4(48). Clayton County

This project consists of the construction of frontage roads along Tara Boulevard/US 41/US 19 from 1-75 to SR 54. A maximum of 100 feet of additional right-of-way would be required for the entire length of the 4.5 mile project corridor.

Clayton County, GA 1976
6546 Entorf, Robert F. Archaeological Assessment of Projects FR-074-2(21) & BHF-074-2(22), Fayette-Clayton Counties

The proposed projects would widen S.R. 85 from S.R. 279 in Fayette County northward to Roberts Drive in Clayton County. Existing right-of-way is 170 feet. Minor right-of-way and slope easements would be required. In addition, the twin bridges over Camp Creek would be widened.

Clayton County, GA 1977