11466 Rotenstein, David S. Archaeological Assessment of Project BRF-148-1(2), Toombs/Tattnall Counties

433'x22' Bridge@ Swift Creek; 433'x22' @Pendleton Creek, 162'x22'@ its overflow; 741' x22' @ Ohoopee River, 190'x22' @ its overflow. Replace bridge at each location with bridges the same length, widened to 40'. All approaches widened to 24' with 8' shoulders, left and right.

Toombs 1986
11467 Entorf, Robert F. Archaeological Assessment of Project BRF-152-1(16), Toombs County

23.81xl 00 1 bridge with timber pilings and caps. Existing R/W is 80 feet. Replace bridge with a triple 91 X9 1 culvert on the existing alignment. Reconstruct app roaches to provide 24 ft. paving and 10 ft. shoulders. On site detour required. No additional R/W or easements.

Toombs 1988
11468 Rotenstein, David S. Archaeological Assessment of Project BRZLB-287(5), Turner County

42’ x 16.1’ timber bridge; no right of way. A proposed double 10’ x 8’ x 36’ concrete bridge culvert will be replaced on existing alignment. Approximately 80’ of right of way will be needed. This road will be closed during construction.

Turner 1985
11469 Entorf, Robert F. Archaeological Assessment of Project BRSLB-2015(2), Troup County

100’ x 32’ bridge; no wetland involvement, no significant archaeological resources.

Troup 1987
11470 Rotenstein, David S. Archaeological Assessment of Project BRSLB-281(3), Towns County

Project begins approximately 400 ft. southeast of the existing bridge on CR 33 and extends 300 ft. past the existing bridge. Proposed structure Double + Double 10' x 10' Concrete Bridge Culvert. Drainage Area - 16.30 sq. mi. 60 ft. of required R/W will be needed.

Towns 1985
11471 Entorf, Robert F. Archaeological Assessment of Project BRS-0722(11), Screven County

Site 1: Project begins 600 ft. east of stream and ends 600 ft. west of stream.

Site 2: Project begins 600 ft. east of stream and ends 500 ft. west of stream.

Site 3: Project begins 600 ft. east of stream and ends 700 ft. west of stream.

Screven 2019
11472 Paglione, Teresa L. Archaeological Assessment of Project BRZLB-259(1), Stewart County

Bridge structure is 200’ x 24;’ no wetland involvement, no potentially significant archaeological resources.

Stewart 1990
11473 Entorf, Robert F. Archaeological Assessment of Project BRF-030-1(8), Stewart County

200’ x 40’ bridge; some wetland involvement, no potentially significant archaeological resources.

Stewart 1988
11474 Entorf, Robert F. Archaeological Assessment of Project BRZLB0283(3), Treutlen County

Some wetland involvement, bridge on CR 109 over Red Bluff Creek.

Treutlen 1989
11475 Entorf, Bob P. Archaeological Assessment of Project STP-0601(1), Glynn County

The proposed project would consist of the widening of 1st Avenue and Bay Street in the City of Brunswick. The proposed widening would begin at the intersection of US 341 /New Castle Street and First Avenue and proceed west along First Avenue to Bay Street.

Glynn 1996