10738 Erickson, Luke W. Archaeological Assessment of a Hancock County Resurfacing Project

This project consists of the milling, leveling, resurfacing, and shoulder building of SR 77 beginning at its intersection with SR 16 and ending at its intersection with SR 15. All work will take place within the existing right-of-way, with no new right-of-way required.

Hancock 2005
10738 Erickson, Luke W. Archaeological Assessment of a Hancock County Resurfacing Project

This project proposes to mill and resurface SR 32 beginning at SR 300 and ending at the Turner/Worth County Line. All work will take place within the existing right-of-way, with no new right-of-way required. Total project length is approximately 12.663 miles.

Hancock 2005
10739 Erickson, Luke W. Archaeological Assessment of a Worth County Resurfacing Project

This project proposes to mill and resurface SR 32 beginning at SR 300 and ending at the Turner/Worth County Line. All work will take place within the existing right-of-way, with no new right-of-way required. Total project length is approximately 12.663 miles.

Worth 2005
10740 Erickson, Luke W. Archaeological Assessment of a Douglas County Resurfacing Project

This project proposes to mill and resurface SR 5 beginning at the Douglas/Carroll County Line and ending at I-20. All work will take place within the existing right-of-way, with no new right-of-way required. Total project length is approximately 13.14 miles.

Douglas 2005
10741 Erickson, Luke W. CSSTP-M003-00(359), P.I. M003359 Clayton County Resurfacing Project

This proposed project consists of the leveling, resurfacing, and 2' shoulder paving and 4' shoulder building of SR 85 beginning at its intersection with SR 331 and ending 120' south of the bridge from the I-75 ramp.

Clayton 2005
10742 McIntosh, Paul Archaeological Assessment of Project STP-M000-00(663), Early County

Archaeological Assessment of Project STP-M000-00(663), Early County, Milling, grooving and resurfacing 2 foot left and right along State Route 62 Bypass, from the intersection of State Route 62 on the west side of Blakely northward and eastward to the State Route 62 intersection on the east side

Early 2000
10743 Erickson, Luke W. Archaeological Assessment of the Forsyth County Resurfacing Project

Archeological Assessment of the Forsyth County Resurfacing Project. This proposed project on SR 369 is 7.4 miles in length beginning 600' west of Holtzclaw Rd. (MP 12.3) and ending at the bridge over Lake Lanier (MP 19.8). The project consists of patching, leveling, and resurfacing.

Forsyth 2003
10744 Erickson, Luke W. Archaeological Assessment of the Forsyth County Resurfacing Project

Archeological Assessment of the Forsyth County Resurfacing Project.

Forsyth 2003
10745 Fleming, Sherry Archaeological Assessment of Project OSAP-98-4(3), Lowndes County

"In compliance with Section 106 of the National Historic Preservation Act of 1966 and amendments thereto, and the Georgia Environmental Policy Act of 1991, project OSAP-98-4(3), Lowndes County has been surveyed with respect to archaeological resources, especially those on or eligible for inclusio

Lowndes 1998
10746 Lotti, Teresa Ann Archaeological Assessment of Project STP-M001-00(772), Decatur and Baker Counties

Archaeological Assessment of Project STP-MOOl-00(772), Decatur and Baker Counties, paving two feet of existing shoulder on each side of SR 253, as well as resurface a portion SR 253 in Decatur and Baker Counties, Georgia. The entire length of the project is 18.63 miles.

Baker 2002