6425 Paglione, Teresa L. Archaeological Assessment of Project SR-2343(10), Gwinnett County

The proposed project consists of the widening and addition at an eastbound lane from the Interstate 85 northbound exit ramp to Crestwood Drive at the Pleasant Hill Road Exit. The total project is approximately 0.5 mile in length.

Columbia 1992
6426 Fernandez-Sardina, Ricardo Assessment of Project MLP-779(3), Gwinnett County

The proposed project would consist of the removal of an existing gravity wall and driveway and the construction of a proposed gravity wall and driveway at Glover Baptist Church on Jimmy Carter Boulevard near it's intersection with Singleton Road. No new right-of-way is required.

Richmond 1992
6427 Fernandez-Sardina, Ricardo Archaeological Evaluation of Project NM-108-1(19), Gwinnett County

The proposed project would reconstruct the Atkinson Road at SR 316 interchange. Atkinson Rd. would be widened from a two lane roadway to a four lane roadway. The existing ramps would be shifted outward from their present location.

Cook 1995
6428 Richardson, Rick R. Archaeological Assessment of Safety Project SR 124/CR 106, Gwinnett County

The proposed project would widen SR 124 at the intersection of CR 106/Old Peachtree Road in Gwinnett County. Left turn lanes would be provided for both northbound and southbound traffic on SR 124. Also, CR 106/Old Peachtree Road would be relocated to intersect with SR 124 at 90 degree angles.

Cook 1996
6429 Duff, Eric Anthony Archaeological Assessment of Project DPI-0010(001)CT 32, Gwinnett County

This project will involve the installation of fiber optic communication cable linking Transportation Control Centers along Jimmy Carter Blvd and Lawrenceville Hwy for a distance of 28.5 km (17.7 mi).

Cook 1995
6430 Paglione, Teresa L. Archaeological Assessment of Project SR-2489(8) and MR-9285(4)

The projects propose to widen and resurface US 23/SR 13 from 2 lanes to 5 lanes with a 20 ft. raised median from Langford to Old Peachtree Road in Duluth.

Cook 1995
6431 Entorf, Robert F. Archaeological Assessment of Project MLP-20(100), Gwinnett County

The proposed project would reconstruct SR 20 on new and existing alignment in Lawrenceville. The proposed project would begin south of Luckie Street at Jackson Street then would extend northerly on new location crossing US 29/Crogan Street and SR 120/Pike Street before tying back into SR 20.

Cook 1994
6432 Richardson, Rick R. Archaeological Assessment of Project STP-0910(13), Gwinnett County

The proposed project consists of intersection improvements at SR 124 and SR 324 by providing alignment corrections to lower the existing higher degree curve.

Cook 1994
6433 Duff, Eric Anthony Archaeological Assessment of Project NH-108-1(27)

Project NH-108-1(27) consists of the proposed interchange construction at the SR 316/Harbins Road intersection in Gwinnett County. Exit and/or entrance ramps would be constructed in all four quadrants of the SR 316/Harbins Road intersection.

Cook 1991
6434 Duff, Eric Anthony Archaeological Assessment of Project NH-108-1(21)

Project NH-108-1(21) would reconstruct and improve SR 316 to include the construction of an interchange at SR 316 and Collins Hill Road in Gwinnett County.

Clayton 1977