11748 Erickson, Luke W. Archeological Assessment of a Paulding County Resurfacing Project (CSSTP-M003-00(213))

Archeological Assessment of a Paulding County Resurfacing Project. This project consists of the resurfacing, milling, grading, and earth shoulder starting on SR 120 Connector, beginning at its intersection with SR 120 and ending at its intersection with SR 92.

Paulding 2005
11749 Rotenstein, David S. Bridge Review Sheet, BRZLB-201(10) Miller County

This is a bridge project, BRZLB-201(10), located in Miller County. The bridge is on CR 188 and crosses Kaney Head Creek. The proposed project will replace the existing structure at Kaney Head Creek with a box culvert.

Miller 1986
11750 Entorf, Robert F. Bridge Categorical Exclusion, BRSLB-1086(9) Oglethorpe County

The proposed project consists of the construction of a replacement bridge on new location over Barrow Creek and the relocation of a section of C.R. 240 south of Arnoldsville.

Oglethorpe 1991
11751 Entorf, Robert F. Bridge Categorical Exclusion, BRS-0506(5) Miller County

This is a bridge project, BRS-0506(5), located in Miller County. The bridge is on SR 45 and crosses Long Branch stream. The existing structure is 120 feet long and 24 feet wide with timber pilings, timber caps, steel stringers, and a concrete deck. The existing ROW is 200 feet.

Miller 1989
11752 Paglione, Teresa L. Bridge Review Sheet, BRZLB-227(10) Pickens County

This is a bridge project, BRZLB-227(10), located in Pickens County. The bridge is on CR 98 and crosses Sharp Mountain Creek. The existing structure has a wooden deck, steel stringers, and iron hand rails. It measures to 30 feet long and 12.3 feet wide. The existing ROW is 40 feet.

Pickens 1985
11753 Entorf, Robert F. Bridge Categorical Exclusion, SR-0630(6) Bryan County

This is a bridge project, SR-0630(6), located in Bryan County. The bridge is on SR 144 and crosses Sterling Creek. The existing structure is 5 lines of 48 inch concrete pipe with concrete endwalls and wingwalls. The existing ROW is 80 feet.

Bryan 1989
11754 Paglione, Teresa L. Bridge Categorical Exclusion, BRS-2862(2) Fannin County

This is a bridge project, BRS-2862(2), located in Fannin County. The bridge is on SR 60 and crosses Hemptown Creek. The existing structure is 300 feet long and 23.8 feet wide and has a concrete deck. The existing ROW is 150 feet.

Fannin 1992
11755 Alston, Robert L. Archaeological Survey of M-4110(1) Bulloch County

M-4110(1), Bulloch County is the widening of a .2 mile section of Tillman Road in Statesboro. This section is located between State Routes 73 and 67. The present right-of-way is 50 feet wide but with the proposed work this will be increased to 100 feet.

Bulloch 1979
11756 Duff, Eric Anthony Archaeological Assessment of District 2 Railroad Grade Crossing Improvement Project, CSSFT-0008-00(546)

The proposed project would improve the existing railroad grade crossing at the intersection of Jaybird-Helena Road/CR 227 over the Norfolk Southern Railway near the City of Chauncey, Georgia in Dodge County.

Dodge 2008
11757 Erickson, Luke W. Archeological Assessment of a Monroe County Resurfacing Project (CSSTP-M003-00(221))

Archeological Assessment of a Monroe County Resurfacing Project. This project consists of milling, leveling, resurfacing, and shoulder building on SR 42 beginning at M.P. 14.58 and ending at the Butts County Line. AJI work will take place within the existing right-of-way.

Monroe 2005