Report Number Author(s) Title Abstract Summary County Year
6315 Bowen, William R. Archaeological Assessment of Project M-9025(8), Cobb County

This is the widening of S.R. 3 (Atlanta Road) from 2/3 to 5 lanes from Spring Road to Hawthorne Road, a distance of 1.0 mile.

Morgan 1978
6316 Entorf, Robert F., Fleming, Sherry Archaeological Assessment of NH-178-1(37), Cobb County

Originally, the proposed project consisted of the addition of left and right turn lanes on the eastbound and westbound approaches of Oglesby and Hill Roads to SR 6/US 278 in Cobb County. The existing traffic signal at Brownsville Road was to be upgraded.

Morgan 1977
6317 Entorf, Robert F., Fleming, Sherry Archaeological Assessment of NH-178-1(37), Cobb County

The proposed project consists of the addition of left and right turn lanes on the eastbound and westbound approaches of Oglesby and Hill Roads to SR 6/US 278 in Cobb County. The existing traffic signal at Brownsville Road would also be upgraded.

Morgan 1977
6318 Paglione, Teresa L. Archaeological Assessment of Projects IR-75-3(165) & MR-9000(21), Cobb County

The projects propose to add additional turning lanes on Delk Road across 1-75, widen the bridge across 1-75 on Delk Road, and to construct a northbound offramp at 1-75 and Delk Road. Two additional lanes are to be constructed on Delk Road between 1-75 and U.S. 41.

Greene 1977
6319 Rotenstein, David S. Archaeological Assessment of Project FR-003-1(30) Douglas/Cobb Counties

This project is the proposed widening of State Route 8/U.S. 78 beginning at Thornton Road/State Route 6 and ending at'the Douglas-Cobb County Line for a distance of 0.6 mile. The proposed widening will be from the existing twolane facility to a four-lane with median facility.

Morgan 1977
6320 Rotenstein, David S. Archaeological Assessment of Project FR-114-1(62), Cobb County

This project is the proposed widening and reconstruction of S.R. 120, Dallas Road, from the Paulding County line to Villa Rica Road. The project would occur within a corridor 100 to 200 feet wide for a distance of 6 miles.

Murray 1976
6321 Rotenstein, David S. Archaeological Assessment of Project FR-003-1(28) Douglas/Cobb Counties

This project begins at the northern terminus of Project FR-003-1(30) and continues northeasterly along State Route 8/U'.S. 78 for a distance of 1.6 miles to the intersection of Austell Road.

Whitfield 1976
6322 Hart, Barry D. Archaeological Assessment of Project M-178-1(18), Cobb County

The project will begin on Lower River Road and will move on new location northwest to intersect Six Flags Road at the Six Flags Road/I-20 intersection. A 350 foot corridor was cleared for the length of the project along the proposed centerline,

Wilkes 1976
6323 Paglione, Teresa L. Archaeological Assessment of Project IR-75-3(165), Cobb County

This project proposes to add additional turning lanes on Delk Road across 1-75, widen the bridge across 1-75 on Delk Road, and to construct a northbound offramp at 1-75 and Delk Road. Two additional lanes are to be constructed on Delk Road between 1-75 and West of Franklin Road.

Gwinnett 1999
6324 Bowen, William R. Archaeological Assessment of Project F-178-1(21), Cobb/Paulding Counties. (Reevaluation)

A corridor consistent with the proposed rights-of-way were surveyed for the entire length of the project.

Wilcox 1993