4148 Joseph, Joseph W. Phase I Archaeological Survey of One Tract, Cobb and Douglas Counties

On October 9' of 2006 New South Associates (NSA) conducted a Phase I Archaeological Survey of an approximately five-acre tract in Cobb and Douglas Counties, Georgia. The goal of the survey was to determine whether the property contained evidence of past human occupation.

Cobb 2006
4149 Tankersley, Matthew The Phase I Archaeological Survey of Five Construction Sites in Cobb County, Georgia

Five tracts ranging between two and five acres are to be the proposed sites for drop shafts associated with a sewer conveyance tunnel system terminating at the Chattahoochee River. The construction sites are located within Cobb County.

Cobb 2006
4150 Matthews, John W. Cultural Resources Survey, Davis Lake Cellular Tower Site, Jackson County, Georgia

Greenhouse Consultants Incorporated was retained by United Consulting to undertake a cultural resources survey and archaeological shovel testing of the proposed Davis Lake Cellular Tower site in Jackson County, Georgia.

Jackson 2000
4151 Pluckhahn, Thomas J. An Archaeological Survey of Four Construction Areas Associated with the Proposed Chattahoochee Tunnel, Cobb County, Georgia

This report presents the results of an archeological survey of four construction areas associated with the proposed Chattahoochee Tunnel in Cobb County, Georgia.

Cobb 1999
4152 VanBuren, Maurie St. George Tap 115kV Transmission Line, St. George 115/25kV Substation, Charlton County, Georgia

In February of 1997, Historic Preservation Consulting was hired by Oglethorpe Power Corporation to conduct a historic resource evaluation of the proposed St. George Tap 115kV Transmission Line and St. George 115/25kV substation project in Charlton County, GEORGIA.

Charlton 1997
4153 Thomas, Larissa A. Cultural Resource Survey for Expansion of the Sewage treatment Facilituy in the City of Emerson, Bartow County, Georgia

This report documents the Phase I cultural resource survey of the tract slated for construction of upgrades to the existing sewage treatment plant for the City of Emerson in Bartow County, Georgia. The archaeological fieldwork was conducted on May 14, 1999, by TRC Garrow Associates, Inc.

Bartow 1999
4154 Cabazares, Joanna Pughes Creek (GASS 5100-026/993496)

The project scope involves the construction of a 300' lattice telecommunications tower located on the north side of Bush Road, adjacent to and north of Interstate 16. The 100' X 100' lease area is located on a parent parcel that consists of approximately 54 acres of raw, wooded land.

Laurens 1999
4155 Thomas, Brian W. Cultural Resource Survey for the Proposed Basin-Toccoa 116kV Transmission Line, Polk County, Tennessee, & Fannin County, Georgia

In April and May, 2000, TRC Garrow Associates, Inc., conducted a cultural resources survey of the proposed TVA Basin-Toccoa 161-kV transmission line and Toccoa 161-kV substation.

Fannin 2000
4156 Thomas, Brian W. Cultural Resources Survey for the Proposed Center Point Substation, Whitfield County, Georgia

In March 2000, TRC Garrow Associates, Inc. (TRC), conducted a cultural resources survey for the proposed Center Point Substation and access road for the Tennessee Valley Authority.

Whitfield 2000
4157 James, Stephen R. Remote-Sensing Survey of the Tybee Island Beach Renourishment Project, Chatham County, Georgia

During the month of September 1997, archaeologists with Panamerican Consultants, Inc., of Memphis, Tennessee, under subcontract to Gulf South Research Corporation of Baton Rouge, Louisiana, conducted a marine remote-sensing survey and terrestrial surface and magnetometer survey of the Tybee Islan

Chatham 1997